02/17/2019
12:44 PM
 
Permit No. D18-0213 Permit Type   DEVELOPMENT Site Address   12501 E MARGINAL WAY S
TUKWILA, WA 98168
Applied   07/13/2018 Applicant   LEO STELLA
Approved   09/04/2018 Owner   INTERNATIONAL GATEWAY EAST
Issued   09/06/2018 Contractor   SABEY CONSTRUCTION INC
Parent Permit No.   Description   LEO STELLA
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

 10/08/2018CONCRETE SLABBill CentenAPPROVED

 12/27/2018EMERGENCY LIGHTINGBrian LuceroAPPROVED12/27/2018 4:31:50 PM after hours inspection for egress lighting

 09/27/2018FOOTINGBill CentenPARTIAL APPROVAL489879/27/2018 12:16:40 PM **SHAKER PIT **- partial approval.
*Pouring bottom double rebar mat w/ #6 bar @ 12’’ o.c. Ea. Way - ok to pour w/ S.I. Approval (Mayes).

 09/21/2018FOUNDATION WALLBill CentenNOT APPROVED434889/21/2018 1:37:32 PM 9/21/2018 - BC **Pit Inspection*** 1. Will need approval for soil bearing pressure along with (8) Pin piles. Geotechnical Engineer to provide approval at next inspection. 2. Need Special Inspectors report for all steel placement prior to calling next inspection. 3. Slab and wall reinforcement is not installed at this time. 4. Call for inspection when ready.

 10/15/2018FRAMINGBill CentenPARTIAL APPROVAL918910/15/2018 2:34:48 PM 10/15/2018 - BC *Framing is approved at Room 122 only. 1. All other areas are waiting on electrical approval.

 01/03/2019GLAZINGBill CentenAPPROVED101590

 10/18/2018LATH/GYPSUM BOARDLee SipePARTIAL APPROVAL44589110/18/2018 10:59:32 AM OK framing, GWB, Insulation rooms 120,121,122,106,105,103,100,107,115

ROOF/CEILING INSULBill Centen

SI-CAST-IN-PLACEBill Centen

SI-CONCRETE CONSTBill Centen

SI-DRIVEN DEEP FOUNDBill Centen

SI-EPOXY/EXP CONCBill Centen

SI-METAL PLATE CONNBill Centen

SI-REINF STEEL-WELDBill Centen

SI-SOILSBill Centen

SI-STRUCT STEELBill Centen

SI-WELDINGBill Centen

 11/09/2018SUSPENDED CEILINGBill CentenPARTIAL APPROVAL18260211/9/2018 2:27:23 PM 11/9/2018 - BC Partial Approval - *Area 1 only - Rooms 120, 121, 122 - ok to install ceiling panels in these rooms only.

 10/17/2018WALL INSULATIONLee SipePARTIAL APPROVAL56420310/17/2018 3:53:43 PM P/A #6 OK insulation Room 122 West wall only. Room 121 South wall only.

 12/27/2018SPRINKLERSBrian LuceroAPPROVED

 11/02/2018SPRINKLER COVERAndy NevensPARTIAL APPROVALPhase 1 approved11/9/2018 11:10:58 AM Ok to cover phase 1 only - highlighted on sprinkler plan Remove all dead pipe throughout Hydro required

 12/27/2018FIRE ALARMBrian LuceroAPPROVED

 12/27/2018FIRE FINALBrian LuceroAPPROVED

 11/19/2018SPRINKLER COVERAndy NevensPARTIAL APPROVALPhases 2 & 311/28/2018 3:09:18 PM Ok to cover phases 2 & 3 highlighted on approved sprinkler plans

 11/30/2018SPRINKLER COVERAndy NevensAPPROVED1/9/2019 4:31:56 PM Ok to cover phase 4 and all other areas

 10/02/2018FOUNDATION WALLBill CentenPARTIAL APPROVAL10/2/2018 2:50:10 PM *Shaker Pit - Foundation Walls - Partial Approval **Ok to pour w/ Special Inspector's approval.

FOOTINGBill Centen

 10/10/2018FOUNDATION WALLLee SipeNOT APPROVED1497910/10/2018 1:48:33 PM No permit or Plans on availible.

 10/17/2018FRAMINGLee SipePARTIAL APPROVAL16452010/17/2018 3:49:21 PM P/A #6 OK insulation: room 122 West wall only. room 121 South wall only.

 12/05/2018FRAMINGBill CentenNOT APPROVED53595212/5/2018 3:31:40 PM 12/5/2018 - BC 1. Clarify Corridor firewall. 2. Existing "B'' Firewalls do not match plan. See detail F/A9.5

 11/26/2018SUSPENDED CEILINGBill CentenPARTIAL APPROVAL1970111/26/2018 12:58:33 PM 11/26/18 B.C. Partial approval. 1. Shaker pit. 2. Corridor 117.

 12/06/2018FRAMINGBill CentenPARTIAL APPROVAL38549312/6/2018 3:28:53 PM 12/6/2018 - BC Hard lid ceiling framing at shaker pit - (approved) Ok to insulate Shaker Pit wall framing - (incomplete) 1. Rated "B" Walls are not per approved plans (See detail F/A9.5). 2. Rated "C" walls are not per approved plans. Missing detail callout.

 01/03/2019LATH/GYPSUM BOARDBill CentenAPPROVED105877

 12/27/2018FRAMINGBill CentenPARTIAL APPROVAL29307612/27/2018 3:39:36 PM Partial approval corridor lid next to shaker room.

BUILDING FINAL**Bill Centen

 01/14/2019FRAMINGRussell SteinikeAPPROVED1041531/14/2019 2:57:07 PM Shaker pit walls.

 12/31/2018BUILDING FINAL**Bill CentenNOT APPROVED27530412/31/2018 2:23:14 PM 12/23/2018 - BC 1. Need to have all exit lighting working and turned to the correct position. 2. Waiting for sound doors (Can not approve framing until these are installed). 3. Environmental area for actual shaker unit is not currently installed or onsite 4. Need to call in all sub permits see permits: PG18-0097, M18-0094, D18-0324. All of which need to be final's prior to Building C of O. 5. Post occupancy load. 6. Submit Mechanical revisions for new Shaker room. 7. Install all brail exit signs. 8. Need to submit Mechanical plan for Air Handler at Exterior pad. HP1 is not on approved plans. 9. Turn exit sign 180 degrees at open office spaces. 10. Not a complete list.

FOUNDATION WALLBill Centen

 10/24/2018FRAMINGBill CentenPARTIAL APPROVAL16497210/24/2018 4:02:35 PM 10/24/2018 - BC 1. Need to submit all framing revisions to building department for approval.

 01/03/2019WALL INSULATIONBill CentenAPPROVED113778

 11/02/2018LATH/GYPSUM BOARDLee SipeNOT APPROVED11374811/2/2018 10:37:05 AM Need approved plans approved through city.

 12/06/2018LATH/GYPSUM BOARDBill CentenCANCELLED261300

 01/03/2019SUSPENDED CEILINGBill CentenAPPROVED84378

 01/03/2019FRAMINGBill CentenPARTIAL APPROVAL931801/3/2019 2:50:22 PM 1/3/2018 - BC Framing - partial approval - 1. Framing is approved except for shaker area. Sound Doors, and Shaker Equipment are not installed at this time.